The Build: Week 21

Wednesday, December 26th – Tuesday, January 1st

This week we saw some decent progress as they started hanging drywall, finishing up the HVAC, and tying up some of the exterior odds and ends. The drywall has made a huge difference in how the interior of the house looks and feels. Having the heat set to 90 doesn’t hurt either.

With the holidays over we hope the crew makes quick work of everything that’s left to be done. We had been told it typically takes 60 days from when the drywall is finished to complete the house so it’s safe to say we won’t be in by the end of January. At this point we’ll reset our expectations and hope to be in by the end of February.

  • Gutters installed
  • HVAC finished
  • Blown in insulation
  • Drywall hung

21 weeks down, 4 8 to go.